A complete mechanical and plumbing gut and replacement including: core restrooms, break rooms, fuel oil system serving three two-megawatt emergency generators, 1,800-ton central plant, 35 air handling units, more than 200 VAV boxes. CPMCA Member: Xcel Mechanical Systems, Inc. Owner: NBCUniversal Contractor: C. W. Driver Architect: Gensler Project Location: Universal City
Pirate-themed Attraction
Xcel Mechanical Systems, Inc. performed the work on this infrastructure remodel project inside one of the world’s most famous theme parks that has called Southern California home since 1955. CPMCA Member: Xcel Mechanical Systems, Inc. Owner: Major Multinational Corporation Contractor: Thor Construction Architect: Major Multinational Corporation Project Location: Anaheim
Cedars-Sinai Advanced Health Sciences Pavilion
Murray Company installed bathrooms, waste and vent risers, core riser for water and medical gas, rooftop HVAC, compressors and pumps, grease interceptors, and multiple tanks for this medical facility built to achieve LEED Gold certification. CPMCA Member: Murray Company Mechanical Contractors Owner: Cedars-Sinai Medical Center Contractor: Hathaway Dinwiddie Architect: HOK Project Location: Los Angeles
Children’s Hospital Los Angeles
Murray Company installed all plumbing systems, waste/vent, water, medical gas, fuel oil, storm drains, site utilities below ground fuel and waste storage tanks for this seven-story hospital building and three-level parking structure. CPMCA Member: Murray Company Mechanical Contractors Owner: Children’s Hospital LA Contractor: Rudolph & Sletten Architect: Zimmer Gunsul Frasca Partnership Project Location: Los Angeles
Torrance Memorial Medical Center
Murray Company coordinated using 3-D BIM with all MEP, steel framing, ceiling supports, concrete and other miscellaneous steel support systems for this new, seven-level patient tower. CPMCA Member: Murray Company Mechanical Contractors Owner: Torrance Memorial Medical Center Contractor: McCarthy Building Companies, Inc. Architect: HMC Architects Project Location: Torrance
Charles Drew University – Life Sciences Research & Nursing Education Building
Installed waste & vent, storm drain, domestic/industrial hot water, domestic/industrial cold water, deionized water, vacuum, low & medium pressure gas, acid waste & vent, carbon dioxide systems. CPMCA Member: All Area Plumbing, Inc. Owner: Charles Drew Univ. Contractor: GKK Works Architect: HOK Project Location: Los Angeles
Cedars-Sinai Medical Center – Saperstein Critical Care Tower
Installed oxygen, medical air, domestic cold & hot water, storm drain, waste & vent systems for the tower which provides 120 ICU patient rooms and 30 monitored patient rooms. CPMCA Member: All Area Plumbing, Inc. Owner: Cedars-Sinai Medical Center Contractor: Tower General Architect: RTKL Assoc., Inc. Project Location: Los Angeles
The Eli and Edythe Broad CIRM Center
The project included lab, hot & cold water, lab waste, lab vacuum, lab air, waste & vent, and prefabricated 99 pipe assemblies with 40 pipe racks for this research facility. CPMCA Member: All Area Plumbing, Inc. Owner: USC Contractor: Morley Construction Company Architect: Zimmer Gunsul Frasca Architects LLP Project Location: Los Angeles
Providence Holy Cross Medical Center
Xcel Mechanical Systems, Inc. installed a new 1,620-ton central plant with three chillers and three cooling towers. The scope of work for this OSHPD project included site work and HVAC piping. CPMCA Member: Xcel Mechanical Systems, Inc. Owner: Providence Holy Cross l Contractor: Swinerton Builders Architect: TMAD Project Location: Mission Hills
29-Palms Cogeneration Plant
Installed heating, hot/chilled water, condensate, waste & vent, domestic hot/cold water, tempered hot water systems in the Marine Corps Air Ground Combat Center addition. CPMCA Member: All Area Plumbing, Inc. Owner: NAVFAC Southwest, Central IPT Contractor: T.B. Penick & Sons, Inc. Architect: Delawie Project Location: Twenty-nine Palms